House of Reps Task Federal Ministries of Water Resources, Power, Works to Complete Abandoned Kafin Zakin Dam Project in Bauchi State

BY OBUTE JAMES

Following a motion of Hon. Abdullahi Sa’ad Abdulkadir, Deputy Chairman, House Committee on Public Account, the House of Representatives has mandated Federal Ministries of Water Resources, Power and Works and Housing to expedite action on the completion of the Kafin Zaki Dam project in Bauchi Stae.

Presenting the motion, Abdulkadir said “ Kafin Zaki Dam Project was initiated in 1973 by the Yakubu Gowon Administration and was proposed as a reservoir with a projected storage capacity of 2,700 million cubic meters onthe Jama’are River.

“Also notes that the Dam was projected to irrigate about 120,000 hectares of arable land to support the production of a potential one million tonnes of sugarcane annually as well as provide over one million jobs in the agricultural sector.

“Further notes that the proposed dam would, when completed, generate about 15 megawatts of hydroelectric power and 45 megawatts or more from bio-fuels, as well as develop about 100,000 tonnes of fisheries annually.”

He said “the Kafin Zaki Dam is a significant project which would greatly enhance the wellbeing of citizens of Bauchi and the neighbouring Jigawa, Yobe and Borno States.

“Also aware that the benefits derivable from the proposed dam project include the development of several agro-allied industries, including sugar refinery, flour mills and vegetables as well as providing recreation and tourism potentials for the region.

“Concerned that the contract for the construction of the dam, which was first awarded to Dwidag Nigeria Limited in 1981 by the Shehu Shagari Administration has since been abandoned for undisclosed reasons and since the abandonment of the first contract, other contracts for construction of the Dam had been awarded to other companies, yet it has never being completed despite promises by successive Administration to ensure its completion.

“Further aware that in 2009, the Federal Ministry of Agriculture and Natural Resources engaged the services of Sahel Consult to conduct an Environmental Impact Assessment on Kafin Zaki Dam and after submitting its Report, controversies have arisen from different quarters against the completion of the project.

“Cognizant that the project would engage thousands of citizens in irrigation farming, thereby raisingtheir means of livelihood and significantly contributing to the economic growth and development ofthe sub-region and the country at large.

Urge the Federal Ministries of Water Resources, Power and Works and Housing to expedite action on the completion of the Kafin Zaki Dam by making provisions for the project in the 2021 Budget estimates.”

The House also mandated the Committees on Water Resources, Power and Works to conduct a public hearing and to liaise with relevant stakeholders with a view to ensuring that all factors militating against the construction of the dam are resolved to ensure that the dam is completed in duetime.